- · Project designs must use run-of-river configurations and cannot involve dam construction or population displacement.
- · Central funding is limited to a Rs 2,585 crore envelope over the five-year implementation window ending 2030–31.
- · Individual project capacities are constrained to the 1–25 MW range.
- · Developers will source activity from an identified site pool totaling 7,133 sites (21,000 MW potential) with 5,100 MW already operational at 1,196 sites.
- · Small hydro project developers
- · Energy investors and financiers
- · State energy departments and utilities
- · Grid operators
- · Implementation deadline: 2030–31